27 developments projects completed in Kunar Province

The National Solidarity Program (NSP) of the Ministry of Rural Rehabilitation and Development (MRRD) has completed 27 uplift projects in various districts of Kunar province.

Costing 40,854,000 AFN, the projects are implemented in Asad Abad, Nurgal, Sarkani and Narang districts of Kunar province.

According to NSP Provincial Manager in Kunar province, these development projects encompass the construction of a 1,858-meters long protection wall, a 11,707-meter pathway, a 1,476- kilometer road, 13 public bathrooms, 11 77-kilowatt micro-hydro power, 3 culverts, one water reservoir, 29 wells and a 9,256- meter extension of a water supply network.

Approximately, 3,701 families in various communities have benefited from these projects.

Since its inception in Kunar province, the NSP has covered 940 communities and has been able to execute 2,139 development projects in different sectors including transport, water and sanitation, irrigation, power, livelihoods, education, etc while the work of another 135 is currently in progress.



Related Articles

A good year for Kanadahar orchard owners

Farmers in southern Kandahar province are enjoying a high production of grapes this season, with the prices of the grapes

Embezzlement in Reconstruction Funds for Zherai district, southern Kandahar

Niaz Mohammad Sarhadi, the district’s administrative head, complained about the fraud committed in funds allocated for the reconstruction projects in

SIGAR releases July 30, 2014 quarterly report to Congress

Appropriations on the U.S. effort to rebuild Afghanistan have totaled $104.1 billion, not including the $5.8 billion requested for fiscal

No comments

Write a comment
No Comments Yet! You can be first to comment this post!

Write a Comment

Your e-mail address will not be published.
Required fields are marked*

Time limit is exhausted. Please reload the CAPTCHA.